As a specialized gas facility company, Gasroad has expertise and diverse technological
capabilities and obeys the principle of no defects through safe and perfect construction.
- Constructing general production laboratories for high-pressure hydrogen gas
-
High-pressure gas facility for various researches and tests, which uses a booster to compress gases such as nitrogen, helium and hydrogen and supplies them to the product to test product pressure resistance, performance and so on
- Prototype is tested by pressurizing it with non-flammable gases such as nitrogen or helium, or hydrogen (H2) boosted by a booster, and a user control program (HMI & GUI) is used via computer
- The booster receives the test gas, pressurizes it up to 105 MPa, stores it temporarily in a buffer and sends it to the prototype installed in the environmental chamber to run each test
- Before high-pressure gas is supplied to the prototype, tests can be done in low-temperature and high-temperature environments ranging from -40℃ to 80℃ using a heat exchanger and an environmental chamber
| Storage capability |
| Container(H2) |
71.0 Nm3 |
| Container(N2) |
35.5 Nm3 |
| Container(He) |
35.5 Nm3 |
| Compressor (booster) |
1480.32Nm3/day |
- Testing equipment with high-temperature air
- Verifying basic performance operation and environmental durability of high-temperature and high-pressure parts (equipment that pressurizes and heats air to the test object, and tests the performance of the prototype by adjusting the flow rate of the supplied gas) / Maximum operating temperature / Cooling water supply tap water pipe
| Maximum operating pressure |
25 barg |
| Maximum operating temperature |
15℃ ~ 530℃ |
| Utility |
Cooling water supply tap water pipe |
- Valve internal pressure testing device
- Facility for testing nitrogen internal pressure reliability in valves
| Maximum operating pressure |
50 MPa |
| Maximum operating temperature |
0℃ ~ 30℃ |
| Processing capacity |
Nitrogen 460.8N㎥ per day |
Gasroad carries out design, production, installation and commissioning of gas facilities and pipelines,
high-pressure pipelines, etc. based on its accumulated technical expertise and quality.
- Constructing liquid nitrogen supply line
-
- Flexible piping and connection/supply to LN2 cart for 2m^3 liquid nitrogen tank
- Monitoring the outlet temperature and pressure and controlling the valve for extreme low temperature by installing a PID controller to control the air outlet temperature up to the maximum target range of between room temperature and -50°C
- Constructing gas supply line system
| Main components |
350bar compressor, constructing high-pressure gas line for clean room |